is seeking certified and qualified DBE subcontractors and/or suppliers to provide Class 2 aggregate base, cold plane, proof roll subgrade, haul off excess materials, trucking, Type a HMA overlay, concrete, curb and gutter, sawcut, grading, gutter apron, stamped concrete, solar powered flashing LED stop sign, demo, signage, thermoplastic striping, ADA parking stall, wheel bumper, markings, paint curbs, striping, monument cover, irrigation system, erosion control plan, traffic control, concrete supplier, paving, electrical, asphalt supplier, electrical, flashing LED Stop Sign, material supplier
W. Kern Ave. Rehabilitation 3rd St. to 5th St.
STPL 5343 (021)
City of McFarland
W. Kern Ave., McFarland, CA, 93250
04-23-2025 at 02:00 PM
Jason Plank
661-399-3759
661-399-3812
34762 Lencioni Avenue , Bakersfield, CA, 93308
PROJECT DETAILS:
34762 LENCIONI AVENUE
BAKERSFIELD, CA 93308
OFFICE: (661) 399-3759
FAX: (661) 399-3812
Cen-Cal Construction is actively soliciting bids from prospective subcontractors or material suppliers whose businesses are California State Certified DBE Contractors or Suppliers. Bids from prospective subcontractors or material suppliers are sought in connection with the Project Named:
W. Kern Ave. Rehabilitation 3rd St. to 5th St.
To be located in the City of McFarland and funded in whole or part by federal funds.
Bid Date: April 23, 2025 @ 2:00PM
Interested certified firms may contact Jason Plank @ (661) 399-3759 or by email at cencalconstruction@ymail.com until 5:00 PM on April 22, 2025.
** 4/22/2025 5PM Due Date for Bids Strictly Enforced to Ensure Time to Finish Bid Paperwork on Day of Bid**
Bid documents and addendums can be obtained from:
City’s Consultant at BHT Engineering Inc., located at 218 S. H Street, Suite 201, Bakersfield CA, 93304.
Contact Juan Pantoja by phone at (661) 558-4641 or email juan@bhtengineering.com for electronic documents.
*Prospective bidders are encouraged to view the project site and required to perform their own due diligence prior to submitting a bid. *
We are an equal opportunity employer and will consider all bids submitted. Subcontractors are required to hold a valid contractors license as well as current Liability, Commercial Auto & Workers Compensation Insurance with applicable limits to meet the contract documents for said project. We encourage DBE certified firms to contact Cen-Cal Construction to learn what assistance we can provide to you such as: lines of credit, insurance, bonds, equipment, supplies, materials, discounts, plans and specifications, technical assistance and services, and other related services. Subcontractor and Trucking quotes/bids must be valid at minimum for the entire duration of the project stated in the contract documents. Subcontractor and Supplier bids are required by 5:00 PM April 22, 2025.
Bids for the followings Items are being requested:
Item 1-Cold Plane 3” of Existing Surface, Proof Roll Subgrade, Haul Off Excess Materials
Item 2-Class 2 Aggregate
Item 3- Type A HMA Overlay
Item 4- Install ADA Curb Ramps
Item 5- Install 8” Thick Concrete Cross Gutter/Apron
Item 6- Install Curb & Gutter-Match Existing
Item 7- Install 8” Thick Re-Stamped Concrete Crosswalk
Item 8- Furnish & Install Solar-Powered Flashing LED Crosswalk
Item 9- Furnish & Install “ALL WAY” Sign
Item 10- Install 12” Solid Limit/Crosswalk (Thermoplastic)
Item 11- Install 24” Solid Crosswalk Line (Thermoplastic)
Item 12- Install White Thermoplastic Pavement Markings
Item 13- Install 6” Yellow Center Line (Detail 22) (Thermoplastic)
Item 14-Install 4” White Stripe-Parking Stalls (Thermoplastic)
Item 15-Intall ADA Parking Stall (Striping, Markings, Signage, Wheel Bumper)
Item 16- Paint Top/Face of Curb Gray Color
Item 17- Adjust/ Relocate Existing Signs
Item 18- Adjust Monument Cover to New Grade
Item 19- Relocate/ Adjust Irrigation System-In Kind
Item 20- Prepare and Implement Erosion Control Plan
Item 21- Temporary Traffic Control